Work hours and Duration dont add up correctly
Hi AmyD,
The duration of a summary task is calculated as the amount of working time
(days, hours, weeks) from the start of the first of the subtasks to the
finish of the last of the subtasks. Because the duration is calculated, you
cannot change the duration of the summary tasks directly. If you change the
durations and links of the subtasks, the summary task duration will
recalculate.
Work is not the same as duration. Work is calculated by:
Task Duration * Resource assignment units = Work
For example: for a task with 1 day (8 hours) duration, if I assign 3
resources all at 100% units, the amount of work on the task is 24 hours. (3
people each working 8 hours but at the same time.)
You may want to take a look at Mike Glen's excellent series of articles at:
http://pubs.logicalexpressions.com/Pub0009/LPMFrame.asp?CMD=ArticleSearch&AUTH=23
Hope this helps. Let us know how you get along.
Julie
|